Conditions
Under what conditions must NYC Advisory Board drawings be filed?
 
A new installation of new equipment totaling 1000KVA or greater.
Exceptions
Exception No. 1:
No submittal is required soley for fire alarm service taps.
Exception No. 2:
No submittal is required for the addition of one 2nd level overcurrent protection device 200A or less.
Any change in an installation with a rating of 1000KVA or larger, up to an including the 2nd level of overcurrent protection unless it was fully described and approved as "future" on the original approved plan.
Any addition to an installation, which would bring the total to 1000KVA or larger.
The addition of any equipment in a room, which would affect clearances around the equipment of a 1000KVA installation.
A new installation or revised installation above 600V irrespective of KVA rating.